Original Cost
₹355 Cr
Baseline estimate
Revised Cost
₹355 Cr
Latest approved cost
Expenditure
₹224 Cr
Spent to date
Utilization
62.9%
Of revised budget
Cost Status
+0.1%
+₹0 Cr increase
Remaining
₹132 Cr
Budget left
Spent
₹224 Cr
Remaining
₹132 Cr
Total
₹355 Cr
Original Cost
₹355 Cr
Revised Cost
₹355 Cr
Increase
+₹0 Cr
Escalation
+0.1%
Project Approved
Construction / Implementation
Original End Date
23/04/2026
Revised Completion
31/10/2026
Completed
Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹355 Cr.
Expenditure stands at ₹224 Cr, which is 62.9% of the revised project cost.
Remaining budget: ₹132 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.