Roads & HighwaysIPM · Central Project +0.1% overrun#618784

Balance works of 4 lane divided carriageway of Missing Link section of NH-39 Rewa Bypass from junction with NH 30 near Bela to Junction with MPRDC ring road near Silpara on SH 9 design length 13.100 km on EPC Mode under Bharatmala Pariyojana in the State of Madhya Pradesh

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹355 CrUtilization: 74.4%Overrun: +₹0 Cr

Original Cost

₹355 Cr

Baseline estimate

+0% overrun

Revised Cost

₹355 Cr

Latest approved cost

Expenditure

₹264 Cr

Spent to date

Utilization

74.4%

Of revised budget

Escalated

Cost Status

+0.1%

+₹0 Cr increase

Remaining

₹91 Cr

Budget left

Budget Utilization

74.4%
0%25%50%75%100%

Spent

₹264 Cr

Remaining

₹91 Cr

Total

₹355 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹355 Cr

Revised Cost

₹355 Cr

Increase

+₹0 Cr

Escalation

+0.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

23/04/2026

Revised Completion

31/01/2027

Completed

Project Details

Project Code618784
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹355 Cr
Revised Cost₹355 Cr
Expenditure₹264 Cr
Original End Date23/04/2026
Revised Date31/01/2027

Project Intelligence

Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹355 Cr.

Expenditure stands at ₹264 Cr, which is 74.4% of the revised project cost.

Remaining budget: ₹91 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance works of 4 lane divided carriageway of Missing Link section of NH-39 Rewa Bypass from junction with NH 30 near Bela to Junction with MPRDC ring road near Silpara on SH 9 design length 13.100 km on EPC Mode under Bharatmala Pariyojana in the State of Madhya Pradesh is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹355.00 Cr, later revised to ₹355.36 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance works of 4 lane divided carriageway of Missing Link section of NH-39 Rew"?
Balance works of 4 lane divided carriageway of Missing Link section of NH-39 Rewa Bypass from junction with NH 30 near Bela to Junction with MPRDC ring road near Silpara on SH 9 design length 13.100 km on EPC Mode under Bharatmala Pariyojana in the State of Madhya Pradesh is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹355 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹355 Cr and has been revised to ₹355 Cr — a cost overrun of +0.1%. Expenditure to date: ₹264 Cr (74.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance works of 4 lane divided carriageway of Missing Link is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618784. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance works of 4 lane divided carriageway of Missing Link is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.