Balance Works for six laning of Sriperumbudur to karaipettai section of NH-4 New NH-48 from 37000 Existing Km 37000 to Km 71015 Existing Km 71000 in Tamilnadu on EPC mode underNHDP Phase-V

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹411 CrUtilization: 39.3%

Original Cost

₹411 Cr

Baseline estimate

On budget

Revised Cost

₹411 Cr

Latest approved cost

Expenditure

₹162 Cr

Spent to date

Utilization

39.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹250 Cr

Budget left

Budget Utilization

39.3%
0%25%50%75%100%

Spent

₹162 Cr

Remaining

₹250 Cr

Total

₹411 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/10/2026

Revised Completion

31/03/2027

Completed

Project Details

Project Code618522
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹411 Cr
Revised Cost₹411 Cr
Expenditure₹162 Cr
Original End Date27/10/2026
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹411 Cr — no cost escalation recorded.

Expenditure stands at ₹162 Cr, which is 39.3% of the revised project cost.

Remaining budget: ₹250 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance Works for six laning of Sriperumbudur to karaipettai section of NH-4 New NH-48 from 37000 Existing Km 37000 to Km 71015 Existing Km 71000 in Tamilnadu on EPC mode underNHDP Phase-V is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹411.00 Cr, later revised to ₹411.16 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance Works for six laning of Sriperumbudur to karaipettai section of NH-4 New"?
Balance Works for six laning of Sriperumbudur to karaipettai section of NH-4 New NH-48 from 37000 Existing Km 37000 to Km 71015 Existing Km 71000 in Tamilnadu on EPC mode underNHDP Phase-V is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹411 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹411 Cr has not been significantly revised. Expenditure: ₹162 Cr (39.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance Works for six laning of Sriperumbudur to karaipettai is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618522. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance Works for six laning of Sriperumbudur to karaipettai is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.