Original Cost
₹411 Cr
Baseline estimate
Revised Cost
₹411 Cr
Latest approved cost
Expenditure
₹120 Cr
Spent to date
Utilization
29.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹291 Cr
Budget left
Spent
₹120 Cr
Remaining
₹291 Cr
Total
₹411 Cr
Project Approved
Construction / Implementation
Original End Date
27/10/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹411 Cr — no cost escalation recorded.
Expenditure stands at ₹120 Cr, which is 29.3% of the revised project cost.
Remaining budget: ₹291 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.