Roads & HighwaysIPM · Central Project#617945

Balance work of NH-66 from design Km 84/00 to Km 87/100 Indapur Bypass and Km 91/600 to Km 99/100 Mangaon Bypass to four lane with paved shoulder in State of Maharashtra under NHO on EPC Mode.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹354 CrUtilization: 44.2%

Original Cost

₹354 Cr

Baseline estimate

On budget

Revised Cost

₹354 Cr

Latest approved cost

Expenditure

₹156 Cr

Spent to date

Utilization

44.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹198 Cr

Budget left

Budget Utilization

44.2%
0%25%50%75%100%

Spent

₹156 Cr

Remaining

₹198 Cr

Total

₹354 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/04/2027

Revised Completion

08/04/2027

Completed

Project Details

Project Code617945
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹354 Cr
Revised Cost₹354 Cr
Expenditure₹156 Cr
Original End Date08/04/2027
Revised Date08/04/2027

Project Intelligence

Project is within original budget of ₹354 Cr — no cost escalation recorded.

Expenditure stands at ₹156 Cr, which is 44.2% of the revised project cost.

Remaining budget: ₹198 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work of NH-66 from design Km 84/00 to Km 87/100 Indapur Bypass and Km 91/600 to Km 99/100 Mangaon Bypass to four lane with paved shoulder in State of Maharashtra under NHO on EPC Mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹354.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work of NH-66 from design Km 84/00 to Km 87/100 Indapur Bypass and Km 91"?
Balance work of NH-66 from design Km 84/00 to Km 87/100 Indapur Bypass and Km 91/600 to Km 99/100 Mangaon Bypass to four lane with paved shoulder in State of Maharashtra under NHO on EPC Mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹354 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹354 Cr has not been significantly revised. Expenditure: ₹156 Cr (44.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance work of NH-66 from design Km 84/00 to Km 87/100 Inda is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617945. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of NH-66 from design Km 84/00 to Km 87/100 Inda is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.