Original Cost
₹1910 Cr
Baseline estimate
Revised Cost
₹2746 Cr
Latest approved cost
Expenditure
₹1340 Cr
Spent to date
Utilization
48.8%
Of revised budget
Cost Status
+43.8%
+₹836 Cr increase
Remaining
₹1405 Cr
Budget left
Spent
₹1340 Cr
Remaining
₹1405 Cr
Total
₹2746 Cr
Original Cost
₹1910 Cr
Revised Cost
₹2746 Cr
Increase
+₹836 Cr
Escalation
+43.8%
Project Approved
Construction / Implementation
Original End Date
15/01/2026
Revised Completion
31/07/2026
Completed
Cost has increased by ₹836 Cr (43.8%) from the original estimate of ₹1910 Cr.
Expenditure stands at ₹1340 Cr, which is 48.8% of the revised project cost.
Remaining budget: ₹1405 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.