Roads & HighwaysIPM · Central Project +43.8% overrun#619089

Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹2746 CrUtilization: 52.3%Overrun: +₹836 Cr

Original Cost

₹1910 Cr

Baseline estimate

+44% overrun

Revised Cost

₹2746 Cr

Latest approved cost

Expenditure

₹1435 Cr

Spent to date

Utilization

52.3%

Of revised budget

Escalated

Cost Status

+43.8%

+₹836 Cr increase

Remaining

₹1311 Cr

Budget left

Budget Utilization

52.3%
0%25%50%75%100%

Spent

₹1435 Cr

Remaining

₹1311 Cr

Total

₹2746 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1910 Cr

Revised Cost

₹2746 Cr

Increase

+₹836 Cr

Escalation

+43.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/01/2026

Revised Completion

30/09/2026

Completed

Project Details

Project Code619089
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹1910 Cr
Revised Cost₹2746 Cr
Expenditure₹1435 Cr
Original End Date15/01/2026
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹836 Cr (43.8%) from the original estimate of ₹1910 Cr.

Expenditure stands at ₹1435 Cr, which is 52.3% of the revised project cost.

Remaining budget: ₹1311 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1910.00 Cr, later revised to ₹2745.74 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km"?
Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹1910 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1910 Cr and has been revised to ₹2746 Cr — a cost overrun of +43.8%. Expenditure to date: ₹1435 Cr (52.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance work of 4L of NarimbangloJatinga Junction- Harangajo is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619089. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of 4L of NarimbangloJatinga Junction- Harangajo is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.