Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27
Original Cost
₹1910 Cr
Baseline estimate
Revised Cost
₹2746 Cr
Latest approved cost
Expenditure
₹1435 Cr
Spent to date
Utilization
52.3%
Of revised budget
Cost Status
+43.8%
+₹836 Cr increase
Remaining
₹1311 Cr
Budget left
Budget Utilization
52.3%Spent
₹1435 Cr
Remaining
₹1311 Cr
Total
₹2746 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1910 Cr
Revised Cost
₹2746 Cr
Increase
+₹836 Cr
Escalation
+43.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/01/2026
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹836 Cr (43.8%) from the original estimate of ₹1910 Cr.
Expenditure stands at ₹1435 Cr, which is 52.3% of the revised project cost.
Remaining budget: ₹1311 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1910.00 Cr, later revised to ₹2745.74 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km"?
- Balance work of 4L of NarimbangloJatinga Junction- Harangajoroad section from Km 0.000 to Km 49.230 of NH-27 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹1910 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1910 Cr and has been revised to ₹2746 Cr — a cost overrun of +43.8%. Expenditure to date: ₹1435 Cr (52.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance work of 4L of NarimbangloJatinga Junction- Harangajo is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619089. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of 4L of NarimbangloJatinga Junction- Harangajo is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.