Balance work for rehabilitation and upgradation of Sidhi -Singrauli Road from Km 82/400 to Km 187/99 Design Length 105.59 Km of NH-39 Old NH-75E to four lane with paved shoulder in the State of Madhya Pradesh on Item Rate Mode.
Original Cost
₹568 Cr
Baseline estimate
Revised Cost
₹568 Cr
Latest approved cost
Expenditure
₹4 Cr
Spent to date
Utilization
0.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹564 Cr
Budget left
Budget Utilization
0.7%Spent
₹4 Cr
Remaining
₹564 Cr
Total
₹568 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/05/2028
Revised Completion
08/05/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹568 Cr — no cost escalation recorded.
Expenditure stands at ₹4 Cr, which is 0.7% of the revised project cost.
Remaining budget: ₹564 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance work for rehabilitation and upgradation of Sidhi -Singrauli Road from Km 82/400 to Km 187/99 Design Length 105.59 Km of NH-39 Old NH-75E to four lane with paved shoulder in the State of Madhya Pradesh on Item Rate Mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹568.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance work for rehabilitation and upgradation of Sidhi -Singrauli Road from Km"?
- Balance work for rehabilitation and upgradation of Sidhi -Singrauli Road from Km 82/400 to Km 187/99 Design Length 105.59 Km of NH-39 Old NH-75E to four lane with paved shoulder in the State of Madhya Pradesh on Item Rate Mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹568 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹568 Cr has not been significantly revised. Expenditure: ₹4 Cr (0.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance work for rehabilitation and upgradation of Sidhi -Si is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619304. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work for rehabilitation and upgradation of Sidhi -Si is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.