101.630 to km.152.520
Original Cost
₹2156 Cr
Baseline estimate
Revised Cost
₹3047 Cr
Latest approved cost
Expenditure
₹1668 Cr
Spent to date
Utilization
54.8%
Of revised cost
Cost Overrun
+41.3%
+₹891 Cr
Remaining
₹1378 Cr
Budget left
Spent
₹1668 Cr
Remaining
₹1378 Cr
Total
₹3047 Cr
54.8%
Utilized
Original Cost
₹2156 Cr
Revised Cost
₹3047 Cr
Increase
+₹891 Cr
Escalation
+41.3%
Project Approved
Construction / Implementation
Original End Date
2024-06-27
Revised Completion
2026-05-31
Completed
Cost has increased by ₹891 Cr (41.3%) from the original estimate of ₹2156 Cr.
Expenditure stands at ₹1668 Cr, which is 54.8% of the revised project cost.
Remaining budget: ₹1378 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.