Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520
Original Cost
₹2156 Cr
Baseline estimate
Revised Cost
₹3047 Cr
Latest approved cost
Expenditure
₹1824 Cr
Spent to date
Utilization
59.9%
Of revised budget
Cost Status
+41.3%
+₹891 Cr increase
Remaining
₹1223 Cr
Budget left
Budget Utilization
59.9%Spent
₹1824 Cr
Remaining
₹1223 Cr
Total
₹3047 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2156 Cr
Revised Cost
₹3047 Cr
Increase
+₹891 Cr
Escalation
+41.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
27/06/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹891 Cr (41.3%) from the original estimate of ₹2156 Cr.
Expenditure stands at ₹1824 Cr, which is 59.9% of the revised project cost.
Remaining budget: ₹1223 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2156.00 Cr, later revised to ₹3046.61 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520"?
- Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2156 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2156 Cr and has been revised to ₹3047 Cr — a cost overrun of +41.3%. Expenditure to date: ₹1824 Cr (59.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618862. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.