Roads & HighwaysIPM · Central Project +41.3% overrun#618862

Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹3047 CrUtilization: 59.9%Overrun: +₹891 Cr

Original Cost

₹2156 Cr

Baseline estimate

+41% overrun

Revised Cost

₹3047 Cr

Latest approved cost

Expenditure

₹1824 Cr

Spent to date

Utilization

59.9%

Of revised budget

Escalated

Cost Status

+41.3%

+₹891 Cr increase

Remaining

₹1223 Cr

Budget left

Budget Utilization

59.9%
0%25%50%75%100%

Spent

₹1824 Cr

Remaining

₹1223 Cr

Total

₹3047 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2156 Cr

Revised Cost

₹3047 Cr

Increase

+₹891 Cr

Escalation

+41.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/06/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code618862
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹2156 Cr
Revised Cost₹3047 Cr
Expenditure₹1824 Cr
Original End Date27/06/2024
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹891 Cr (41.3%) from the original estimate of ₹2156 Cr.

Expenditure stands at ₹1824 Cr, which is 59.9% of the revised project cost.

Remaining budget: ₹1223 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2156.00 Cr, later revised to ₹3046.61 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520"?
Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2156 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2156 Cr and has been revised to ₹3047 Cr — a cost overrun of +41.3%. Expenditure to date: ₹1824 Cr (59.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618862. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.