Mokama Km 197.900
Original Cost
₹1183 Cr
Baseline estimate
Revised Cost
₹1899 Cr
Latest approved cost
Expenditure
₹843 Cr
Spent to date
Utilization
44.4%
Of revised cost
Cost Overrun
+60.5%
+₹716 Cr
Remaining
₹1056 Cr
Budget left
Spent
₹843 Cr
Remaining
₹1056 Cr
Total
₹1899 Cr
44.4%
Utilized
Original Cost
₹1183 Cr
Revised Cost
₹1899 Cr
Increase
+₹716 Cr
Escalation
+60.5%
Project Approved
Construction / Implementation
Original End Date
2019-12-10
Revised Completion
2026-05-31
Completed
Cost has increased by ₹716 Cr (60.5%) from the original estimate of ₹1183 Cr.
Expenditure stands at ₹843 Cr, which is 44.4% of the revised project cost.
Remaining budget: ₹1056 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.