Original Cost
₹844 Cr
Baseline estimate
Revised Cost
₹844 Cr
Latest approved cost
Expenditure
₹1 Cr
Spent to date
Utilization
0.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹843 Cr
Budget left
Spent
₹1 Cr
Remaining
₹843 Cr
Total
₹844 Cr
Project Approved
Construction / Implementation
Original End Date
22/03/2028
Revised Completion
22/03/2028
Completed
Project is within original budget of ₹844 Cr — no cost escalation recorded.
Expenditure stands at ₹1 Cr, which is 0.1% of the revised project cost.
Remaining budget: ₹843 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.