Pkg-II
Original Cost
₹985 Cr
Baseline estimate
Revised Cost
₹828 Cr
Latest approved cost
Expenditure
₹798 Cr
Spent to date
Utilization
96.4%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹29 Cr
Budget left
Spent
₹798 Cr
Remaining
₹29 Cr
Total
₹828 Cr
96.4%
Utilized
Project Approved
Construction / Implementation
Original End Date
2023-07-16
Revised Completion
2025-11-30
Completed
Project is within original budget of ₹985 Cr — no cost escalation recorded.
Expenditure stands at ₹798 Cr, which is 96.4% of the revised project cost.
Remaining budget: ₹29 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.