Roads & HighwaysIPM · Central Project#618795

Amritsar Bypass Pkg III from km. 71.496 to km. 105.158

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹1228 CrUtilization: 99.6%

Original Cost

₹1475 Cr

Baseline estimate

On budget

Revised Cost

₹1228 Cr

Latest approved cost

Expenditure

₹1224 Cr

Spent to date

Utilization

99.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹5 Cr

Budget left

Budget Utilization

99.6%
0%25%50%75%100%

Spent

₹1224 Cr

Remaining

₹5 Cr

Total

₹1228 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/08/2024

Revised Completion

31/12/2026

Completed

Project Details

Project Code618795
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹1475 Cr
Revised Cost₹1228 Cr
Expenditure₹1224 Cr
Original End Date30/08/2024
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹1475 Cr — no cost escalation recorded.

Expenditure stands at ₹1224 Cr, which is 99.6% of the revised project cost.

Remaining budget: ₹5 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Amritsar Bypass Pkg III from km. 71.496 to km. 105.158 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1475.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Amritsar Bypass Pkg III from km. 71.496 to km. 105.158"?
Amritsar Bypass Pkg III from km. 71.496 to km. 105.158 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1475 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1475 Cr and has been revised to ₹1228 Cr — a cost overrun of -16.7%. Expenditure to date: ₹1224 Cr (99.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Amritsar Bypass Pkg III from km. 71.496 to km. 105.158 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618795. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Amritsar Bypass Pkg III from km. 71.496 to km. 105.158 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.