Additional works under BM1 to ensure road safety under 6L of Bengaluru Mysuru Access control with close toll from Km.17.300 to Km.136.300 of NH-275
Original Cost
₹738 Cr
Baseline estimate
Revised Cost
₹738 Cr
Latest approved cost
Expenditure
₹33 Cr
Spent to date
Utilization
4.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹705 Cr
Budget left
Budget Utilization
4.4%Spent
₹33 Cr
Remaining
₹705 Cr
Total
₹738 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/01/2028
Revised Completion
26/05/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹738 Cr — no cost escalation recorded.
Expenditure stands at ₹33 Cr, which is 4.4% of the revised project cost.
Remaining budget: ₹705 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Additional works under BM1 to ensure road safety under 6L of Bengaluru Mysuru Access control with close toll from Km.17.300 to Km.136.300 of NH-275 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹738.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Additional works under BM1 to ensure road safety under 6L of Bengaluru Mysuru A"?
- Additional works under BM1 to ensure road safety under 6L of Bengaluru Mysuru Access control with close toll from Km.17.300 to Km.136.300 of NH-275 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹738 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹738 Cr has not been significantly revised. Expenditure: ₹33 Cr (4.4% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Additional works under BM1 to ensure road safety under 6L of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618707. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Additional works under BM1 to ensure road safety under 6L of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.