Roads & HighwaysIPM · Central Project +1.6% overrun#618620

Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹211 CrUtilization: 73.5%Overrun: +₹3 Cr

Original Cost

₹208 Cr

Baseline estimate

+2% overrun

Revised Cost

₹211 Cr

Latest approved cost

Expenditure

₹155 Cr

Spent to date

Utilization

73.5%

Of revised budget

Escalated

Cost Status

+1.6%

+₹3 Cr increase

Remaining

₹56 Cr

Budget left

Budget Utilization

73.5%
0%25%50%75%100%

Spent

₹155 Cr

Remaining

₹56 Cr

Total

₹211 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹208 Cr

Revised Cost

₹211 Cr

Increase

+₹3 Cr

Escalation

+1.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/07/2024

Revised Completion

31/03/2027

Completed

Project Details

Project Code618620
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹208 Cr
Revised Cost₹211 Cr
Expenditure₹155 Cr
Original End Date17/07/2024
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹3 Cr (1.6%) from the original estimate of ₹208 Cr.

Expenditure stands at ₹155 Cr, which is 73.5% of the revised project cost.

Remaining budget: ₹56 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹208.00 Cr, later revised to ₹211.27 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-"?
Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹208 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹208 Cr and has been revised to ₹211 Cr — a cost overrun of +1.6%. Expenditure to date: ₹155 Cr (73.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Additional works 2VUPs, MR-10 junction flyover and underpass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618620. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Additional works 2VUPs, MR-10 junction flyover and underpass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.