Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode
Original Cost
₹208 Cr
Baseline estimate
Revised Cost
₹211 Cr
Latest approved cost
Expenditure
₹155 Cr
Spent to date
Utilization
73.5%
Of revised budget
Cost Status
+1.6%
+₹3 Cr increase
Remaining
₹56 Cr
Budget left
Budget Utilization
73.5%Spent
₹155 Cr
Remaining
₹56 Cr
Total
₹211 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹208 Cr
Revised Cost
₹211 Cr
Increase
+₹3 Cr
Escalation
+1.6%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/07/2024
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹3 Cr (1.6%) from the original estimate of ₹208 Cr.
Expenditure stands at ₹155 Cr, which is 73.5% of the revised project cost.
Remaining budget: ₹56 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹208.00 Cr, later revised to ₹211.27 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-"?
- Additional works 2VUPs, MR-10 junction flyover and underpass in Six lane Indore-Dewas section of NH-52 in the state of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹208 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹208 Cr and has been revised to ₹211 Cr — a cost overrun of +1.6%. Expenditure to date: ₹155 Cr (73.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Additional works 2VUPs, MR-10 junction flyover and underpass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618620. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Additional works 2VUPs, MR-10 junction flyover and underpass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.