Original Cost
₹208 Cr
Baseline estimate
Revised Cost
₹211 Cr
Latest approved cost
Expenditure
₹131 Cr
Spent to date
Utilization
61.9%
Of revised budget
Cost Status
+1.6%
+₹3 Cr increase
Remaining
₹81 Cr
Budget left
Spent
₹131 Cr
Remaining
₹81 Cr
Total
₹211 Cr
Original Cost
₹208 Cr
Revised Cost
₹211 Cr
Increase
+₹3 Cr
Escalation
+1.6%
Project Approved
Construction / Implementation
Original End Date
17/07/2024
Revised Completion
18/02/2027
Completed
Cost has increased by ₹3 Cr (1.6%) from the original estimate of ₹208 Cr.
Expenditure stands at ₹131 Cr, which is 61.9% of the revised project cost.
Remaining budget: ₹81 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.