Original Cost
₹2068 Cr
Baseline estimate
Revised Cost
₹2670 Cr
Latest approved cost
Expenditure
₹1910 Cr
Spent to date
Utilization
71.5%
Of revised budget
Cost Status
+29.1%
+₹602 Cr increase
Remaining
₹760 Cr
Budget left
Spent
₹1910 Cr
Remaining
₹760 Cr
Total
₹2670 Cr
Original Cost
₹2068 Cr
Revised Cost
₹2670 Cr
Increase
+₹602 Cr
Escalation
+29.1%
Project Approved
Construction / Implementation
Original End Date
16/10/2021
Revised Completion
30/06/2026
Completed
Cost has increased by ₹602 Cr (29.1%) from the original estimate of ₹2068 Cr.
Expenditure stands at ₹1910 Cr, which is 71.5% of the revised project cost.
Remaining budget: ₹760 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.