Original Cost
₹797 Cr
Baseline estimate
Revised Cost
₹560 Cr
Latest approved cost
Expenditure
₹500 Cr
Spent to date
Utilization
89.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹60 Cr
Budget left
Spent
₹500 Cr
Remaining
₹60 Cr
Total
₹560 Cr
Project Approved
Construction / Implementation
Original End Date
03/11/2024
Revised Completion
15/04/2026
Completed
Project is within original budget of ₹797 Cr — no cost escalation recorded.
Expenditure stands at ₹500 Cr, which is 89.2% of the revised project cost.
Remaining budget: ₹60 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.