Original Cost
₹1440 Cr
Baseline estimate
Revised Cost
₹1440 Cr
Latest approved cost
Expenditure
₹735 Cr
Spent to date
Utilization
51.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹705 Cr
Budget left
Spent
₹735 Cr
Remaining
₹705 Cr
Total
₹1440 Cr
Project Approved
Construction / Implementation
Original End Date
24/01/2025
Revised Completion
15/09/2026
Completed
Project is within original budget of ₹1440 Cr — no cost escalation recorded.
Expenditure stands at ₹735 Cr, which is 51.0% of the revised project cost.
Remaining budget: ₹705 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.