Original Cost
₹1925 Cr
Baseline estimate
Revised Cost
₹1887 Cr
Latest approved cost
Expenditure
₹948 Cr
Spent to date
Utilization
50.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹940 Cr
Budget left
Spent
₹948 Cr
Remaining
₹940 Cr
Total
₹1887 Cr
Project Approved
Construction / Implementation
Original End Date
05/12/2024
Revised Completion
10/04/2026
Completed
Project is within original budget of ₹1925 Cr — no cost escalation recorded.
Expenditure stands at ₹948 Cr, which is 50.2% of the revised project cost.
Remaining budget: ₹940 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.