Original Cost
₹2105 Cr
Baseline estimate
Revised Cost
₹2066 Cr
Latest approved cost
Expenditure
₹795 Cr
Spent to date
Utilization
38.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1271 Cr
Budget left
Spent
₹795 Cr
Remaining
₹1271 Cr
Total
₹2066 Cr
Project Approved
Construction / Implementation
Original End Date
22/10/2025
Revised Completion
30/11/2026
Completed
Project is within original budget of ₹2105 Cr — no cost escalation recorded.
Expenditure stands at ₹795 Cr, which is 38.5% of the revised project cost.
Remaining budget: ₹1271 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.