Roads & HighwaysIPM · Central Project#619211

6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 97.000 to Km. 162.500 in Yadgir of NH-150C Pkg-III

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹2066 CrUtilization: 48.6%

Original Cost

₹2105 Cr

Baseline estimate

On budget

Revised Cost

₹2066 Cr

Latest approved cost

Expenditure

₹1004 Cr

Spent to date

Utilization

48.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1062 Cr

Budget left

Budget Utilization

48.6%
0%25%50%75%100%

Spent

₹1004 Cr

Remaining

₹1062 Cr

Total

₹2066 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/10/2025

Revised Completion

31/03/2027

Completed

Project Details

Project Code619211
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹2105 Cr
Revised Cost₹2066 Cr
Expenditure₹1004 Cr
Original End Date22/10/2025
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹2105 Cr — no cost escalation recorded.

Expenditure stands at ₹1004 Cr, which is 48.6% of the revised project cost.

Remaining budget: ₹1062 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 97.000 to Km. 162.500 in Yadgir of NH-150C Pkg-III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2105.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 97.0"?
6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 97.000 to Km. 162.500 in Yadgir of NH-150C Pkg-III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹2105 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2105 Cr and has been revised to ₹2066 Cr — a cost overrun of -1.9%. Expenditure to date: ₹1004 Cr (48.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi V is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619211. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi V is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.