Original Cost
₹2356 Cr
Baseline estimate
Revised Cost
₹1923 Cr
Latest approved cost
Expenditure
₹888 Cr
Spent to date
Utilization
46.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1036 Cr
Budget left
Spent
₹888 Cr
Remaining
₹1036 Cr
Total
₹1923 Cr
Project Approved
Construction / Implementation
Original End Date
27/06/2025
Revised Completion
30/11/2026
Completed
Project is within original budget of ₹2356 Cr — no cost escalation recorded.
Expenditure stands at ₹888 Cr, which is 46.2% of the revised project cost.
Remaining budget: ₹1036 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.