Original Cost
₹666 Cr
Baseline estimate
Revised Cost
₹666 Cr
Latest approved cost
Expenditure
₹512 Cr
Spent to date
Utilization
76.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹153 Cr
Budget left
Spent
₹512 Cr
Remaining
₹153 Cr
Total
₹666 Cr
Project Approved
Construction / Implementation
Original End Date
30/07/2021
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹666 Cr — no cost escalation recorded.
Expenditure stands at ₹512 Cr, which is 76.9% of the revised project cost.
Remaining budget: ₹153 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.