Roads & HighwaysIPM · Central Project +17.0% overrun#618579

6L of Anandapuram Pendurthi Anakapalli Section from km. 681.000 to km. 731.780 of NH-16

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹2957 CrUtilization: 80.4%Overrun: +₹430 Cr

Original Cost

₹2527 Cr

Baseline estimate

+17% overrun

Revised Cost

₹2957 Cr

Latest approved cost

Expenditure

₹2379 Cr

Spent to date

Utilization

80.4%

Of revised budget

Escalated

Cost Status

+17.0%

+₹430 Cr increase

Remaining

₹579 Cr

Budget left

Budget Utilization

80.4%
0%25%50%75%100%

Spent

₹2379 Cr

Remaining

₹579 Cr

Total

₹2957 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2527 Cr

Revised Cost

₹2957 Cr

Increase

+₹430 Cr

Escalation

+17.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/07/2021

Revised Completion

31/10/2026

Completed

Project Details

Project Code618579
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2527 Cr
Revised Cost₹2957 Cr
Expenditure₹2379 Cr
Original End Date01/07/2021
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹430 Cr (17.0%) from the original estimate of ₹2527 Cr.

Expenditure stands at ₹2379 Cr, which is 80.4% of the revised project cost.

Remaining budget: ₹579 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L of Anandapuram Pendurthi Anakapalli Section from km. 681.000 to km. 731.780 of NH-16 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2527.00 Cr, later revised to ₹2957.25 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L of Anandapuram Pendurthi Anakapalli Section from km. 681.000 to km. 731.780 o"?
6L of Anandapuram Pendurthi Anakapalli Section from km. 681.000 to km. 731.780 of NH-16 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹2527 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2527 Cr and has been revised to ₹2957 Cr — a cost overrun of +17%. Expenditure to date: ₹2379 Cr (80.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L of Anandapuram Pendurthi Anakapalli Section from km. 681. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618579. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L of Anandapuram Pendurthi Anakapalli Section from km. 681. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.