From KM. 116000 to KM. 151200 Package-6
Original Cost
₹1916 Cr
Baseline estimate
Revised Cost
₹1920 Cr
Latest approved cost
Expenditure
₹65 Cr
Spent to date
Utilization
3.4%
Of revised cost
Cost Overrun
+0.2%
+₹4 Cr
Remaining
₹1856 Cr
Budget left
Spent
₹65 Cr
Remaining
₹1856 Cr
Total
₹1920 Cr
3.4%
Utilized
Original Cost
₹1916 Cr
Revised Cost
₹1920 Cr
Increase
+₹4 Cr
Escalation
+0.2%
Project Approved
Construction / Implementation
Original End Date
2027-09-03
Revised Completion
2027-09-03
Completed
Cost has increased by ₹4 Cr (0.2%) from the original estimate of ₹1916 Cr.
Expenditure stands at ₹65 Cr, which is 3.4% of the revised project cost.
Remaining budget: ₹1856 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.