Chandauli-Chainpur road near Khainti village from Km. 0.000 to Km. 27.000 - Pkg-1
Original Cost
₹1433 Cr
Baseline estimate
Revised Cost
₹1564 Cr
Latest approved cost
Expenditure
₹374 Cr
Spent to date
Utilization
23.9%
Of revised cost
Cost Overrun
+9.2%
+₹131 Cr
Remaining
₹1191 Cr
Budget left
Spent
₹374 Cr
Remaining
₹1191 Cr
Total
₹1564 Cr
23.9%
Utilized
Original Cost
₹1433 Cr
Revised Cost
₹1564 Cr
Increase
+₹131 Cr
Escalation
+9.2%
Project Approved
Construction / Implementation
Original End Date
2026-11-24
Revised Completion
2027-05-18
Completed
Cost has increased by ₹131 Cr (9.2%) from the original estimate of ₹1433 Cr.
Expenditure stands at ₹374 Cr, which is 23.9% of the revised project cost.
Remaining budget: ₹1191 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.