Roads & HighwaysIPM · Central Project +9.2% overrun#618728

6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with NH-19 & Varanasi Ring Road near Rewasa village to junction with Chandauli-Chainpur road near Khainti village from Km. 0.000 to Km. 27.000 - Pkg-1

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹1564 CrUtilization: 38.2%Overrun: +₹131 Cr

Original Cost

₹1433 Cr

Baseline estimate

+9% overrun

Revised Cost

₹1564 Cr

Latest approved cost

Expenditure

₹598 Cr

Spent to date

Utilization

38.2%

Of revised budget

Escalated

Cost Status

+9.2%

+₹131 Cr increase

Remaining

₹966 Cr

Budget left

Budget Utilization

38.2%
0%25%50%75%100%

Spent

₹598 Cr

Remaining

₹966 Cr

Total

₹1564 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1433 Cr

Revised Cost

₹1564 Cr

Increase

+₹131 Cr

Escalation

+9.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/11/2026

Revised Completion

18/05/2027

Completed

Project Details

Project Code618728
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1433 Cr
Revised Cost₹1564 Cr
Expenditure₹598 Cr
Original End Date24/11/2026
Revised Date18/05/2027

Project Intelligence

Cost has increased by ₹131 Cr (9.2%) from the original estimate of ₹1433 Cr.

Expenditure stands at ₹598 Cr, which is 38.2% of the revised project cost.

Remaining budget: ₹966 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with NH-19 & Varanasi Ring Road near Rewasa village to junction with Chandauli-Chainpur road near Khainti village from Km. 0.000 to Km. 27.000 - Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1433.00 Cr, later revised to ₹1564.15 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with NH-19 & Varanas"?
6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with NH-19 & Varanasi Ring Road near Rewasa village to junction with Chandauli-Chainpur road near Khainti village from Km. 0.000 to Km. 27.000 - Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1433 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1433 Cr and has been revised to ₹1564 Cr — a cost overrun of +9.2%. Expenditure to date: ₹598 Cr (38.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618728. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.