Roads & HighwaysIPM · Central Project +28.1% overrun#618680

6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹1913 CrUtilization: 56.9%Overrun: +₹420 Cr

Original Cost

₹1493 Cr

Baseline estimate

+28% overrun

Revised Cost

₹1913 Cr

Latest approved cost

Expenditure

₹1089 Cr

Spent to date

Utilization

56.9%

Of revised budget

Escalated

Cost Status

+28.1%

+₹420 Cr increase

Remaining

₹824 Cr

Budget left

Budget Utilization

56.9%
0%25%50%75%100%

Spent

₹1089 Cr

Remaining

₹824 Cr

Total

₹1913 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1493 Cr

Revised Cost

₹1913 Cr

Increase

+₹420 Cr

Escalation

+28.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/10/2024

Revised Completion

31/08/2026

Completed

Project Details

Project Code618680
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-07

Financial Summary

Original Cost₹1493 Cr
Revised Cost₹1913 Cr
Expenditure₹1089 Cr
Original End Date17/10/2024
Revised Date31/08/2026

Project Intelligence

Cost has increased by ₹420 Cr (28.1%) from the original estimate of ₹1493 Cr.

Expenditure stands at ₹1089 Cr, which is 56.9% of the revised project cost.

Remaining budget: ₹824 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1493.00 Cr, later revised to ₹1912.84 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 36"?
6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹1493 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1493 Cr and has been revised to ₹1913 Cr — a cost overrun of +28.1%. Expenditure to date: ₹1089 Cr (56.9% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
6L Greenfield Kandili - Aluru Section of NH-130-CD Road fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618680. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Kandili - Aluru Section of NH-130-CD Road fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.