6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8
Original Cost
₹1493 Cr
Baseline estimate
Revised Cost
₹1913 Cr
Latest approved cost
Expenditure
₹1089 Cr
Spent to date
Utilization
56.9%
Of revised budget
Cost Status
+28.1%
+₹420 Cr increase
Remaining
₹824 Cr
Budget left
Budget Utilization
56.9%Spent
₹1089 Cr
Remaining
₹824 Cr
Total
₹1913 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1493 Cr
Revised Cost
₹1913 Cr
Increase
+₹420 Cr
Escalation
+28.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/10/2024
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹420 Cr (28.1%) from the original estimate of ₹1493 Cr.
Expenditure stands at ₹1089 Cr, which is 56.9% of the revised project cost.
Remaining budget: ₹824 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1493.00 Cr, later revised to ₹1912.84 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 36"?
- 6L Greenfield Kandili - Aluru Section of NH-130-CD Road from km 342500 to km 365033 Package-OD-8 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹1493 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1493 Cr and has been revised to ₹1913 Cr — a cost overrun of +28.1%. Expenditure to date: ₹1089 Cr (56.9% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- 6L Greenfield Kandili - Aluru Section of NH-130-CD Road fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618680. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Kandili - Aluru Section of NH-130-CD Road fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.