6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Road from km 249000 to km 293000 Package OD-5
Original Cost
₹1540 Cr
Baseline estimate
Revised Cost
₹1918 Cr
Latest approved cost
Expenditure
₹1027 Cr
Spent to date
Utilization
53.5%
Of revised budget
Cost Status
+24.6%
+₹378 Cr increase
Remaining
₹892 Cr
Budget left
Budget Utilization
53.5%Spent
₹1027 Cr
Remaining
₹892 Cr
Total
₹1918 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1540 Cr
Revised Cost
₹1918 Cr
Increase
+₹378 Cr
Escalation
+24.6%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/05/2024
Revised Completion
30/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹378 Cr (24.6%) from the original estimate of ₹1540 Cr.
Expenditure stands at ₹1027 Cr, which is 53.5% of the revised project cost.
Remaining budget: ₹892 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Road from km 249000 to km 293000 Package OD-5 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1540.00 Cr, later revised to ₹1918.49 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Road from km 249000 to"?
- 6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Road from km 249000 to km 293000 Package OD-5 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹1540 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1540 Cr and has been revised to ₹1918 Cr — a cost overrun of +24.6%. Expenditure to date: ₹1027 Cr (53.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Ro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618677. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Greenfield Kaliagura Baunsaguar Section of NH-130-CD Ro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.