Original Cost
₹1540 Cr
Baseline estimate
Revised Cost
₹1918 Cr
Latest approved cost
Expenditure
₹979 Cr
Spent to date
Utilization
51.0%
Of revised budget
Cost Status
+24.6%
+₹378 Cr increase
Remaining
₹940 Cr
Budget left
Spent
₹979 Cr
Remaining
₹940 Cr
Total
₹1918 Cr
Original Cost
₹1540 Cr
Revised Cost
₹1918 Cr
Increase
+₹378 Cr
Escalation
+24.6%
Project Approved
Construction / Implementation
Original End Date
29/05/2024
Revised Completion
30/11/2026
Completed
Cost has increased by ₹378 Cr (24.6%) from the original estimate of ₹1540 Cr.
Expenditure stands at ₹979 Cr, which is 51.0% of the revised project cost.
Remaining budget: ₹940 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.