Roads & HighwaysIPM · Central Project#618704

6L Flyover including RE Wall approaches with Flexible Pavement in the Elephant Corridor of Angul Sambalpur Section of NH-42 New NH-55 Km.202.533

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹106 CrUtilization: 99.8%

Original Cost

₹151 Cr

Baseline estimate

On budget

Revised Cost

₹106 Cr

Latest approved cost

Expenditure

₹106 Cr

Spent to date

Utilization

99.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

99.8%
0%25%50%75%100%

Spent

₹106 Cr

Remaining

₹0 Cr

Total

₹106 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/06/2026

Revised Completion

30/09/2026

Completed

Project Details

Project Code618704
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹151 Cr
Revised Cost₹106 Cr
Expenditure₹106 Cr
Original End Date20/06/2026
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹151 Cr — no cost escalation recorded.

Expenditure stands at ₹106 Cr, which is 99.8% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Flyover including RE Wall approaches with Flexible Pavement in the Elephant Corridor of Angul Sambalpur Section of NH-42 New NH-55 Km.202.533 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹151.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Flyover including RE Wall approaches with Flexible Pavement in the Elephant C"?
6L Flyover including RE Wall approaches with Flexible Pavement in the Elephant Corridor of Angul Sambalpur Section of NH-42 New NH-55 Km.202.533 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹151 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹151 Cr and has been revised to ₹106 Cr — a cost overrun of -29.6%. Expenditure to date: ₹106 Cr (99.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L Flyover including RE Wall approaches with Flexible Paveme is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618704. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Flyover including RE Wall approaches with Flexible Paveme is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.