Original Cost
₹1973 Cr
Baseline estimate
Revised Cost
₹1943 Cr
Latest approved cost
Expenditure
₹766 Cr
Spent to date
Utilization
39.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1177 Cr
Budget left
Spent
₹766 Cr
Remaining
₹1177 Cr
Total
₹1943 Cr
Project Approved
Construction / Implementation
Original End Date
30/07/2025
Revised Completion
10/04/2026
Completed
Project is within original budget of ₹1973 Cr — no cost escalation recorded.
Expenditure stands at ₹766 Cr, which is 39.4% of the revised project cost.
Remaining budget: ₹1177 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.