Original Cost
₹907 Cr
Baseline estimate
Revised Cost
₹1021 Cr
Latest approved cost
Expenditure
₹490 Cr
Spent to date
Utilization
48.0%
Of revised budget
Cost Status
+12.5%
+₹114 Cr increase
Remaining
₹530 Cr
Budget left
Spent
₹490 Cr
Remaining
₹530 Cr
Total
₹1021 Cr
Original Cost
₹907 Cr
Revised Cost
₹1021 Cr
Increase
+₹114 Cr
Escalation
+12.5%
Project Approved
Construction / Implementation
Original End Date
13/09/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹114 Cr (12.5%) from the original estimate of ₹907 Cr.
Expenditure stands at ₹490 Cr, which is 48.0% of the revised project cost.
Remaining budget: ₹530 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.