Roads & HighwaysIPM · Central Project#618757

6L access controlled Highway from Km 40080 to Km 86513 Mator to Barodameo Section

Ministry of Road Transport & HighwaysRajasthan
Revised Cost: ₹1566 CrUtilization: 46.2%

Original Cost

₹2010 Cr

Baseline estimate

On budget

Revised Cost

₹1566 Cr

Latest approved cost

Expenditure

₹724 Cr

Spent to date

Utilization

46.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹842 Cr

Budget left

Budget Utilization

46.2%
0%25%50%75%100%

Spent

₹724 Cr

Remaining

₹842 Cr

Total

₹1566 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/03/2026

Revised Completion

30/06/2027

Completed

Project Details

Project Code618757
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹2010 Cr
Revised Cost₹1566 Cr
Expenditure₹724 Cr
Original End Date14/03/2026
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹2010 Cr — no cost escalation recorded.

Expenditure stands at ₹724 Cr, which is 46.2% of the revised project cost.

Remaining budget: ₹842 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L access controlled Highway from Km 40080 to Km 86513 Mator to Barodameo Section is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2010.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L access controlled Highway from Km 40080 to Km 86513 Mator to Barodameo Sectio"?
6L access controlled Highway from Km 40080 to Km 86513 Mator to Barodameo Section is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Rajasthan. Original cost: ₹2010 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2010 Cr and has been revised to ₹1566 Cr — a cost overrun of -22.1%. Expenditure to date: ₹724 Cr (46.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L access controlled Highway from Km 40080 to Km 86513 Mator is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618757. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L access controlled Highway from Km 40080 to Km 86513 Mator is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.