Original Cost
₹972 Cr
Baseline estimate
Revised Cost
₹1044 Cr
Latest approved cost
Expenditure
₹443 Cr
Spent to date
Utilization
42.5%
Of revised budget
Cost Status
+7.4%
+₹72 Cr increase
Remaining
₹601 Cr
Budget left
Spent
₹443 Cr
Remaining
₹601 Cr
Total
₹1044 Cr
Original Cost
₹972 Cr
Revised Cost
₹1044 Cr
Increase
+₹72 Cr
Escalation
+7.4%
Project Approved
Construction / Implementation
Original End Date
03/01/2025
Revised Completion
31/08/2026
Completed
Cost has increased by ₹72 Cr (7.4%) from the original estimate of ₹972 Cr.
Expenditure stands at ₹443 Cr, which is 42.5% of the revised project cost.
Remaining budget: ₹601 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.