6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1
Original Cost
₹972 Cr
Baseline estimate
Revised Cost
₹1044 Cr
Latest approved cost
Expenditure
₹459 Cr
Spent to date
Utilization
44.0%
Of revised budget
Cost Status
+7.4%
+₹72 Cr increase
Remaining
₹585 Cr
Budget left
Budget Utilization
44.0%Spent
₹459 Cr
Remaining
₹585 Cr
Total
₹1044 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹972 Cr
Revised Cost
₹1044 Cr
Increase
+₹72 Cr
Escalation
+7.4%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/01/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹72 Cr (7.4%) from the original estimate of ₹972 Cr.
Expenditure stands at ₹459 Cr, which is 44.0% of the revised project cost.
Remaining budget: ₹585 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹972.00 Cr, later revised to ₹1044.06 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "6L Access Controlled Greenfield Highway of Nandinne village to Julekal village f"?
- 6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹972 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹972 Cr and has been revised to ₹1044 Cr — a cost overrun of +7.4%. Expenditure to date: ₹459 Cr (44.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 6L Access Controlled Greenfield Highway of Nandinne village is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618632. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Access Controlled Greenfield Highway of Nandinne village is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.