Roads & HighwaysIPM · Central Project +7.4% overrun#618632

6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹1044 CrUtilization: 44.0%Overrun: +₹72 Cr

Original Cost

₹972 Cr

Baseline estimate

+7% overrun

Revised Cost

₹1044 Cr

Latest approved cost

Expenditure

₹459 Cr

Spent to date

Utilization

44.0%

Of revised budget

Escalated

Cost Status

+7.4%

+₹72 Cr increase

Remaining

₹585 Cr

Budget left

Budget Utilization

44.0%
0%25%50%75%100%

Spent

₹459 Cr

Remaining

₹585 Cr

Total

₹1044 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹972 Cr

Revised Cost

₹1044 Cr

Increase

+₹72 Cr

Escalation

+7.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/01/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code618632
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹972 Cr
Revised Cost₹1044 Cr
Expenditure₹459 Cr
Original End Date03/01/2025
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹72 Cr (7.4%) from the original estimate of ₹972 Cr.

Expenditure stands at ₹459 Cr, which is 44.0% of the revised project cost.

Remaining budget: ₹585 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹972.00 Cr, later revised to ₹1044.06 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6L Access Controlled Greenfield Highway of Nandinne village to Julekal village f"?
6L Access Controlled Greenfield Highway of Nandinne village to Julekal village from Km 202.900 to Km 242.200 Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹972 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹972 Cr and has been revised to ₹1044 Cr — a cost overrun of +7.4%. Expenditure to date: ₹459 Cr (44.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6L Access Controlled Greenfield Highway of Nandinne village is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618632. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6L Access Controlled Greenfield Highway of Nandinne village is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.