Original Cost
₹751 Cr
Baseline estimate
Revised Cost
₹627 Cr
Latest approved cost
Expenditure
₹226 Cr
Spent to date
Utilization
36.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹400 Cr
Budget left
Spent
₹226 Cr
Remaining
₹400 Cr
Total
₹627 Cr
Project Approved
Construction / Implementation
Original End Date
01/03/2026
Revised Completion
28/02/2027
Completed
Project is within original budget of ₹751 Cr — no cost escalation recorded.
Expenditure stands at ₹226 Cr, which is 36.1% of the revised project cost.
Remaining budget: ₹400 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.