Original Cost
₹747 Cr
Baseline estimate
Revised Cost
₹627 Cr
Latest approved cost
Expenditure
₹228 Cr
Spent to date
Utilization
36.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹399 Cr
Budget left
Spent
₹228 Cr
Remaining
₹399 Cr
Total
₹627 Cr
Project Approved
Construction / Implementation
Original End Date
10/02/2026
Revised Completion
31/05/2027
Completed
Project is within original budget of ₹747 Cr — no cost escalation recorded.
Expenditure stands at ₹228 Cr, which is 36.4% of the revised project cost.
Remaining budget: ₹399 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.