Original Cost
₹1092 Cr
Baseline estimate
Revised Cost
₹956 Cr
Latest approved cost
Expenditure
₹200 Cr
Spent to date
Utilization
20.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹756 Cr
Budget left
Spent
₹200 Cr
Remaining
₹756 Cr
Total
₹956 Cr
Project Approved
Construction / Implementation
Original End Date
07/02/2027
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹1092 Cr — no cost escalation recorded.
Expenditure stands at ₹200 Cr, which is 20.9% of the revised project cost.
Remaining budget: ₹756 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.