Original Cost
₹987 Cr
Baseline estimate
Revised Cost
₹848 Cr
Latest approved cost
Expenditure
₹320 Cr
Spent to date
Utilization
37.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹528 Cr
Budget left
Spent
₹320 Cr
Remaining
₹528 Cr
Total
₹848 Cr
Project Approved
Construction / Implementation
Original End Date
06/03/2026
Revised Completion
30/04/2027
Completed
Project is within original budget of ₹987 Cr — no cost escalation recorded.
Expenditure stands at ₹320 Cr, which is 37.7% of the revised project cost.
Remaining budget: ₹528 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.