Original Cost
₹1492 Cr
Baseline estimate
Revised Cost
₹1123 Cr
Latest approved cost
Expenditure
₹721 Cr
Spent to date
Utilization
64.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹402 Cr
Budget left
Spent
₹721 Cr
Remaining
₹402 Cr
Total
₹1123 Cr
Project Approved
Construction / Implementation
Original End Date
01/05/2025
Revised Completion
28/02/2027
Completed
Project is within original budget of ₹1492 Cr — no cost escalation recorded.
Expenditure stands at ₹721 Cr, which is 64.2% of the revised project cost.
Remaining budget: ₹402 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.