Roads & HighwaysIPM · Central Project +6.3% overrun#617913

6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Section of Hyderabad-Bangalore section of NH-44 Under NHO EPC basis in the state of Telangana

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹301 CrUtilization: 90.1%Overrun: +₹18 Cr

Original Cost

₹283 Cr

Baseline estimate

+6% overrun

Revised Cost

₹301 Cr

Latest approved cost

Expenditure

₹271 Cr

Spent to date

Utilization

90.1%

Of revised budget

Escalated

Cost Status

+6.3%

+₹18 Cr increase

Remaining

₹30 Cr

Budget left

Budget Utilization

90.1%
0%25%50%75%100%

Spent

₹271 Cr

Remaining

₹30 Cr

Total

₹301 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹283 Cr

Revised Cost

₹301 Cr

Increase

+₹18 Cr

Escalation

+6.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/05/2020

Revised Completion

30/06/2026

Completed

Project Details

Project Code617913
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹283 Cr
Revised Cost₹301 Cr
Expenditure₹271 Cr
Original End Date09/05/2020
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹18 Cr (6.3%) from the original estimate of ₹283 Cr.

Expenditure stands at ₹271 Cr, which is 90.1% of the revised project cost.

Remaining budget: ₹30 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Section of Hyderabad-Bangalore section of NH-44 Under NHO EPC basis in the state of Telangana is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹283.00 Cr, later revised to ₹300.70 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Section of Hyderabad-Ba"?
6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Section of Hyderabad-Bangalore section of NH-44 Under NHO EPC basis in the state of Telangana is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹283 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹283 Cr and has been revised to ₹301 Cr — a cost overrun of +6.3%. Expenditure to date: ₹271 Cr (90.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Sec is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617913. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Sec is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.