Original Cost
₹1364 Cr
Baseline estimate
Revised Cost
₹1692 Cr
Latest approved cost
Expenditure
₹615 Cr
Spent to date
Utilization
36.3%
Of revised budget
Cost Status
+24.1%
+₹328 Cr increase
Remaining
₹1077 Cr
Budget left
Spent
₹615 Cr
Remaining
₹1077 Cr
Total
₹1692 Cr
Original Cost
₹1364 Cr
Revised Cost
₹1692 Cr
Increase
+₹328 Cr
Escalation
+24.1%
Project Approved
Construction / Implementation
Original End Date
14/10/2021
Revised Completion
30/06/2026
Completed
Cost has increased by ₹328 Cr (24.1%) from the original estimate of ₹1364 Cr.
Expenditure stands at ₹615 Cr, which is 36.3% of the revised project cost.
Remaining budget: ₹1077 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.