Roads & HighwaysIPM · Central Project#618770

4L Spur of Panipat - Shamli connecting NH-709AD Panipat Shamli Muzaffarnagar and NH-709A Karnal Meerut bypassing Shamli district UP

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹273 CrUtilization: 85.2%

Original Cost

₹516 Cr

Baseline estimate

On budget

Revised Cost

₹273 Cr

Latest approved cost

Expenditure

₹233 Cr

Spent to date

Utilization

85.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹40 Cr

Budget left

Budget Utilization

85.2%
0%25%50%75%100%

Spent

₹233 Cr

Remaining

₹40 Cr

Total

₹273 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

13/10/2024

Revised Completion

17/03/2025

Completed

Project Details

Project Code618770
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-05

Financial Summary

Original Cost₹516 Cr
Revised Cost₹273 Cr
Expenditure₹233 Cr
Original End Date13/10/2024
Revised Date17/03/2025

Project Intelligence

Project is within original budget of ₹516 Cr — no cost escalation recorded.

Expenditure stands at ₹233 Cr, which is 85.2% of the revised project cost.

Remaining budget: ₹40 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Spur of Panipat - Shamli connecting NH-709AD Panipat Shamli Muzaffarnagar and NH-709A Karnal Meerut bypassing Shamli district UP is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹516.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Spur of Panipat - Shamli connecting NH-709AD Panipat Shamli Muzaffarnagar a"?
4L Spur of Panipat - Shamli connecting NH-709AD Panipat Shamli Muzaffarnagar and NH-709A Karnal Meerut bypassing Shamli district UP is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹516 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹516 Cr and has been revised to ₹273 Cr — a cost overrun of -47%. Expenditure to date: ₹233 Cr (85.2% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L Spur of Panipat - Shamli connecting NH-709AD Panipat Sha is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618770. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Spur of Panipat - Shamli connecting NH-709AD Panipat Sha is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.