4L Ring road/bypass around Srinagar city from km 0.000 to km 42.100 Phase-I

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹2605 CrUtilization: 71.9%

Original Cost

₹2920 Cr

Baseline estimate

On budget

Revised Cost

₹2605 Cr

Latest approved cost

Expenditure

₹1874 Cr

Spent to date

Utilization

71.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹731 Cr

Budget left

Budget Utilization

71.9%
0%25%50%75%100%

Spent

₹1874 Cr

Remaining

₹731 Cr

Total

₹2605 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/02/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code618541
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹2920 Cr
Revised Cost₹2605 Cr
Expenditure₹1874 Cr
Original End Date02/02/2024
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹2920 Cr — no cost escalation recorded.

Expenditure stands at ₹1874 Cr, which is 71.9% of the revised project cost.

Remaining budget: ₹731 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Ring road/bypass around Srinagar city from km 0.000 to km 42.100 Phase-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2920.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Ring road/bypass around Srinagar city from km 0.000 to km 42.100 Phase-I"?
4L Ring road/bypass around Srinagar city from km 0.000 to km 42.100 Phase-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹2920 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2920 Cr and has been revised to ₹2605 Cr — a cost overrun of -10.8%. Expenditure to date: ₹1874 Cr (71.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Ring road/bypass around Srinagar city from km 0.000 to km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618541. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Ring road/bypass around Srinagar city from km 0.000 to km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.