Original Cost
₹2920 Cr
Baseline estimate
Revised Cost
₹2605 Cr
Latest approved cost
Expenditure
₹1774 Cr
Spent to date
Utilization
68.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹831 Cr
Budget left
Spent
₹1774 Cr
Remaining
₹831 Cr
Total
₹2605 Cr
Project Approved
Construction / Implementation
Original End Date
02/02/2024
Revised Completion
31/10/2026
Completed
Project is within original budget of ₹2920 Cr — no cost escalation recorded.
Expenditure stands at ₹1774 Cr, which is 68.1% of the revised project cost.
Remaining budget: ₹831 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.