Original Cost
₹884 Cr
Baseline estimate
Revised Cost
₹1727 Cr
Latest approved cost
Expenditure
₹62 Cr
Spent to date
Utilization
3.6%
Of revised budget
Cost Status
+95.3%
+₹843 Cr increase
Remaining
₹1665 Cr
Budget left
Spent
₹62 Cr
Remaining
₹1665 Cr
Total
₹1727 Cr
Original Cost
₹884 Cr
Revised Cost
₹1727 Cr
Increase
+₹843 Cr
Escalation
+95.3%
Project Approved
Construction / Implementation
Original End Date
02/04/2027
Revised Completion
22/07/2028
Completed
Cost has increased by ₹843 Cr (95.3%) from the original estimate of ₹884 Cr.
Expenditure stands at ₹62 Cr, which is 3.6% of the revised project cost.
Remaining budget: ₹1665 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.