4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to Atmakur Existing Km.73.000/Design Km 66.115 of NH340C Package2
Original Cost
₹887 Cr
Baseline estimate
Revised Cost
₹913 Cr
Latest approved cost
Expenditure
₹374 Cr
Spent to date
Utilization
41.0%
Of revised budget
Cost Status
+2.9%
+₹26 Cr increase
Remaining
₹539 Cr
Budget left
Budget Utilization
41.0%Spent
₹374 Cr
Remaining
₹539 Cr
Total
₹913 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹887 Cr
Revised Cost
₹913 Cr
Increase
+₹26 Cr
Escalation
+2.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/11/2025
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹26 Cr (2.9%) from the original estimate of ₹887 Cr.
Expenditure stands at ₹374 Cr, which is 41.0% of the revised project cost.
Remaining budget: ₹539 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to Atmakur Existing Km.73.000/Design Km 66.115 of NH340C Package2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹887.00 Cr, later revised to ₹913.03 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to Atmakur Existing Km.7"?
- 4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to Atmakur Existing Km.73.000/Design Km 66.115 of NH340C Package2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹887 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹887 Cr and has been revised to ₹913 Cr — a cost overrun of +2.9%. Expenditure to date: ₹374 Cr (41.0% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to A is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618919. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L PS from Mandlem Existing Km. 38.000/Design Km.30.600 to A is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.