Roads & HighwaysIPM · Central Project#618891

4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from Km 41.000 to Km 58.450

Ministry of Road Transport & HighwaysHimachal Pradesh
Revised Cost: ₹787 CrUtilization: 18.5%

Original Cost

₹1244 Cr

Baseline estimate

On budget

Revised Cost

₹787 Cr

Latest approved cost

Expenditure

₹146 Cr

Spent to date

Utilization

18.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹641 Cr

Budget left

Budget Utilization

18.5%
0%25%50%75%100%

Spent

₹146 Cr

Remaining

₹641 Cr

Total

₹787 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/05/2027

Revised Completion

09/09/2027

Completed

Project Details

Project Code618891
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1244 Cr
Revised Cost₹787 Cr
Expenditure₹146 Cr
Original End Date12/05/2027
Revised Date09/09/2027

Project Intelligence

Project is within original budget of ₹1244 Cr — no cost escalation recorded.

Expenditure stands at ₹146 Cr, which is 18.5% of the revised project cost.

Remaining budget: ₹641 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from Km 41.000 to Km 58.450 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1244.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from Km 41.000 to Km 58.4"?
4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from Km 41.000 to Km 58.450 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹1244 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1244 Cr and has been revised to ₹787 Cr — a cost overrun of -36.7%. Expenditure to date: ₹146 Cr (18.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618891. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.