Roads & HighwaysIPM · Central Project +32.1% overrun#619219

4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121.900 Banawara of NH-206

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1990 CrUtilization: 65.3%Overrun: +₹484 Cr

Original Cost

₹1506 Cr

Baseline estimate

+32% overrun

Revised Cost

₹1990 Cr

Latest approved cost

Expenditure

₹1300 Cr

Spent to date

Utilization

65.3%

Of revised budget

Escalated

Cost Status

+32.1%

+₹484 Cr increase

Remaining

₹690 Cr

Budget left

Budget Utilization

65.3%
0%25%50%75%100%

Spent

₹1300 Cr

Remaining

₹690 Cr

Total

₹1990 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1506 Cr

Revised Cost

₹1990 Cr

Increase

+₹484 Cr

Escalation

+32.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/10/2021

Revised Completion

31/12/2026

Completed

Project Details

Project Code619219
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1506 Cr
Revised Cost₹1990 Cr
Expenditure₹1300 Cr
Original End Date14/10/2021
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹484 Cr (32.1%) from the original estimate of ₹1506 Cr.

Expenditure stands at ₹1300 Cr, which is 65.3% of the revised project cost.

Remaining budget: ₹690 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121.900 Banawara of NH-206 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1506.00 Cr, later revised to ₹1989.89 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121.900 Banawara of NH-2"?
4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121.900 Banawara of NH-206 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1506 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1506 Cr and has been revised to ₹1990 Cr — a cost overrun of +32.1%. Expenditure to date: ₹1300 Cr (65.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619219. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.