Original Cost
₹1506 Cr
Baseline estimate
Revised Cost
₹1990 Cr
Latest approved cost
Expenditure
₹657 Cr
Spent to date
Utilization
33.0%
Of revised budget
Cost Status
+32.1%
+₹484 Cr increase
Remaining
₹1333 Cr
Budget left
Spent
₹657 Cr
Remaining
₹1333 Cr
Total
₹1990 Cr
Original Cost
₹1506 Cr
Revised Cost
₹1990 Cr
Increase
+₹484 Cr
Escalation
+32.1%
Project Approved
Construction / Implementation
Original End Date
14/10/2021
Revised Completion
31/12/2026
Completed
Cost has increased by ₹484 Cr (32.1%) from the original estimate of ₹1506 Cr.
Expenditure stands at ₹657 Cr, which is 33.0% of the revised project cost.
Remaining budget: ₹1333 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.