4L of Thirumangalam to Vadugapatti section from km 0.000 to km 36.000 of NH-744
Original Cost
₹1077 Cr
Baseline estimate
Revised Cost
₹792 Cr
Latest approved cost
Expenditure
₹686 Cr
Spent to date
Utilization
86.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹106 Cr
Budget left
Budget Utilization
86.6%Spent
₹686 Cr
Remaining
₹106 Cr
Total
₹792 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
21/02/2025
Revised Completion
25/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1077 Cr — no cost escalation recorded.
Expenditure stands at ₹686 Cr, which is 86.6% of the revised project cost.
Remaining budget: ₹106 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Thirumangalam to Vadugapatti section from km 0.000 to km 36.000 of NH-744 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1077.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Thirumangalam to Vadugapatti section from km 0.000 to km 36.000 of NH-744"?
- 4L of Thirumangalam to Vadugapatti section from km 0.000 to km 36.000 of NH-744 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1077 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1077 Cr and has been revised to ₹792 Cr — a cost overrun of -26.5%. Expenditure to date: ₹686 Cr (86.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Thirumangalam to Vadugapatti section from km 0.000 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618744. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Thirumangalam to Vadugapatti section from km 0.000 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.