Roads & HighwaysIPM · Central Project#618798

4L of Sonauli - Gorakhpur

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹2275 CrUtilization: 58.5%

Original Cost

₹2556 Cr

Baseline estimate

On budget

Revised Cost

₹2275 Cr

Latest approved cost

Expenditure

₹1331 Cr

Spent to date

Utilization

58.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹944 Cr

Budget left

Budget Utilization

58.5%
0%25%50%75%100%

Spent

₹1331 Cr

Remaining

₹944 Cr

Total

₹2275 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

05/03/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618798
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2556 Cr
Revised Cost₹2275 Cr
Expenditure₹1331 Cr
Original End Date05/03/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹2556 Cr — no cost escalation recorded.

Expenditure stands at ₹1331 Cr, which is 58.5% of the revised project cost.

Remaining budget: ₹944 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Sonauli - Gorakhpur is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2556.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Sonauli - Gorakhpur"?
4L of Sonauli - Gorakhpur is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2556 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2556 Cr and has been revised to ₹2275 Cr — a cost overrun of -11%. Expenditure to date: ₹1331 Cr (58.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Sonauli - Gorakhpur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618798. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Sonauli - Gorakhpur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.