Original Cost
₹1215 Cr
Baseline estimate
Revised Cost
₹1462 Cr
Latest approved cost
Expenditure
₹864 Cr
Spent to date
Utilization
59.1%
Of revised budget
Cost Status
+20.3%
+₹247 Cr increase
Remaining
₹598 Cr
Budget left
Spent
₹864 Cr
Remaining
₹598 Cr
Total
₹1462 Cr
Original Cost
₹1215 Cr
Revised Cost
₹1462 Cr
Increase
+₹247 Cr
Escalation
+20.3%
Project Approved
Construction / Implementation
Original End Date
20/06/2025
Revised Completion
31/12/2026
Completed
Cost has increased by ₹247 Cr (20.3%) from the original estimate of ₹1215 Cr.
Expenditure stands at ₹864 Cr, which is 59.1% of the revised project cost.
Remaining budget: ₹598 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.