Roads & HighwaysIPM · Central Project +20.3% overrun#618644

4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of NH- 320BPKG-II

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹1462 CrUtilization: 68.1%Overrun: +₹247 Cr

Original Cost

₹1215 Cr

Baseline estimate

+20% overrun

Revised Cost

₹1462 Cr

Latest approved cost

Expenditure

₹995 Cr

Spent to date

Utilization

68.1%

Of revised budget

Escalated

Cost Status

+20.3%

+₹247 Cr increase

Remaining

₹467 Cr

Budget left

Budget Utilization

68.1%
0%25%50%75%100%

Spent

₹995 Cr

Remaining

₹467 Cr

Total

₹1462 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1215 Cr

Revised Cost

₹1462 Cr

Increase

+₹247 Cr

Escalation

+20.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/06/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618644
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹1215 Cr
Revised Cost₹1462 Cr
Expenditure₹995 Cr
Original End Date20/06/2025
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹247 Cr (20.3%) from the original estimate of ₹1215 Cr.

Expenditure stands at ₹995 Cr, which is 68.1% of the revised project cost.

Remaining budget: ₹467 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of NH- 320BPKG-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1215.00 Cr, later revised to ₹1462.19 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of NH- 320BPKG-II"?
4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of NH- 320BPKG-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1215 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1215 Cr and has been revised to ₹1462 Cr — a cost overrun of +20.3%. Expenditure to date: ₹995 Cr (68.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of N is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618644. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Ormanjhi-Gola section from Km 81.450 to Km 53.600 of N is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.