4L of Munger Mirzachauki section from Munger to Kharia village junction from Km 69520 to Km 95580 Pkg-1
Original Cost
₹1660 Cr
Baseline estimate
Revised Cost
₹1697 Cr
Latest approved cost
Expenditure
₹686 Cr
Spent to date
Utilization
40.4%
Of revised budget
Cost Status
+2.2%
+₹37 Cr increase
Remaining
₹1011 Cr
Budget left
Budget Utilization
40.4%Spent
₹686 Cr
Remaining
₹1011 Cr
Total
₹1697 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1660 Cr
Revised Cost
₹1697 Cr
Increase
+₹37 Cr
Escalation
+2.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/03/2024
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹37 Cr (2.2%) from the original estimate of ₹1660 Cr.
Expenditure stands at ₹686 Cr, which is 40.4% of the revised project cost.
Remaining budget: ₹1011 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Munger Mirzachauki section from Munger to Kharia village junction from Km 69520 to Km 95580 Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1660.00 Cr, later revised to ₹1696.66 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Munger Mirzachauki section from Munger to Kharia village junction from Km"?
- 4L of Munger Mirzachauki section from Munger to Kharia village junction from Km 69520 to Km 95580 Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹1660 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1660 Cr and has been revised to ₹1697 Cr — a cost overrun of +2.2%. Expenditure to date: ₹686 Cr (40.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Munger Mirzachauki section from Munger to Kharia vill is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619289. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Munger Mirzachauki section from Munger to Kharia vill is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.