junction from Km 69520 to Km 95580 Pkg-1
Original Cost
₹1660 Cr
Baseline estimate
Revised Cost
₹1697 Cr
Latest approved cost
Expenditure
₹506 Cr
Spent to date
Utilization
29.8%
Of revised cost
Cost Overrun
+2.2%
+₹37 Cr
Remaining
₹1190 Cr
Budget left
Spent
₹506 Cr
Remaining
₹1190 Cr
Total
₹1697 Cr
29.8%
Utilized
Original Cost
₹1660 Cr
Revised Cost
₹1697 Cr
Increase
+₹37 Cr
Escalation
+2.2%
Project Approved
Construction / Implementation
Original End Date
2024-03-30
Revised Completion
2026-06-30
Completed
Cost has increased by ₹37 Cr (2.2%) from the original estimate of ₹1660 Cr.
Expenditure stands at ₹506 Cr, which is 29.8% of the revised project cost.
Remaining budget: ₹1190 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.