4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.900 of NH-71Package-I
Original Cost
₹1877 Cr
Baseline estimate
Revised Cost
₹1994 Cr
Latest approved cost
Expenditure
₹1183 Cr
Spent to date
Utilization
59.3%
Of revised budget
Cost Status
+6.2%
+₹117 Cr increase
Remaining
₹811 Cr
Budget left
Budget Utilization
59.3%Spent
₹1183 Cr
Remaining
₹811 Cr
Total
₹1994 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1877 Cr
Revised Cost
₹1994 Cr
Increase
+₹117 Cr
Escalation
+6.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
12/01/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹117 Cr (6.2%) from the original estimate of ₹1877 Cr.
Expenditure stands at ₹1183 Cr, which is 59.3% of the revised project cost.
Remaining budget: ₹811 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.900 of NH-71Package-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1877.00 Cr, later revised to ₹1994.10 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.900 of NH-71Package-I"?
- 4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.900 of NH-71Package-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹1877 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1877 Cr and has been revised to ₹1994 Cr — a cost overrun of +6.2%. Expenditure to date: ₹1183 Cr (59.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.9 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618778. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Madanapalle to Pileru Section from Km 0.000 to Km 55.9 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.