Original Cost
₹1877 Cr
Baseline estimate
Revised Cost
₹1994 Cr
Latest approved cost
Expenditure
₹1147 Cr
Spent to date
Utilization
57.5%
Of revised budget
Cost Status
+6.2%
+₹117 Cr increase
Remaining
₹847 Cr
Budget left
Spent
₹1147 Cr
Remaining
₹847 Cr
Total
₹1994 Cr
Original Cost
₹1877 Cr
Revised Cost
₹1994 Cr
Increase
+₹117 Cr
Escalation
+6.2%
Project Approved
Construction / Implementation
Original End Date
12/01/2025
Revised Completion
30/06/2026
Completed
Cost has increased by ₹117 Cr (6.2%) from the original estimate of ₹1877 Cr.
Expenditure stands at ₹1147 Cr, which is 57.5% of the revised project cost.
Remaining budget: ₹847 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.