Original Cost
₹1703 Cr
Baseline estimate
Revised Cost
₹2649 Cr
Latest approved cost
Expenditure
₹981 Cr
Spent to date
Utilization
37.0%
Of revised budget
Cost Status
+55.5%
+₹946 Cr increase
Remaining
₹1668 Cr
Budget left
Spent
₹981 Cr
Remaining
₹1668 Cr
Total
₹2649 Cr
Original Cost
₹1703 Cr
Revised Cost
₹2649 Cr
Increase
+₹946 Cr
Escalation
+55.5%
Project Approved
Construction / Implementation
Original End Date
21/04/2026
Revised Completion
31/12/2027
Completed
Cost has increased by ₹946 Cr (55.5%) from the original estimate of ₹1703 Cr.
Expenditure stands at ₹981 Cr, which is 37.0% of the revised project cost.
Remaining budget: ₹1668 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.