4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km 272.571
Original Cost
₹2532 Cr
Baseline estimate
Revised Cost
₹3619 Cr
Latest approved cost
Expenditure
₹1361 Cr
Spent to date
Utilization
37.6%
Of revised budget
Cost Status
+42.9%
+₹1087 Cr increase
Remaining
₹2258 Cr
Budget left
Budget Utilization
37.6%Spent
₹1361 Cr
Remaining
₹2258 Cr
Total
₹3619 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2532 Cr
Revised Cost
₹3619 Cr
Increase
+₹1087 Cr
Escalation
+42.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/03/2020
Revised Completion
31/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1087 Cr (42.9%) from the original estimate of ₹2532 Cr.
Expenditure stands at ₹1361 Cr, which is 37.6% of the revised project cost.
Remaining budget: ₹2258 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km 272.571 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2532.00 Cr, later revised to ₹3619.32 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km 272.571"?
- 4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km 272.571 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹2532 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2532 Cr and has been revised to ₹3619 Cr — a cost overrun of +42.9%. Expenditure to date: ₹1361 Cr (37.6% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619121. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.