4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of Old NH-20 New NH-154 Package-IA
Original Cost
₹1002 Cr
Baseline estimate
Revised Cost
₹1363 Cr
Latest approved cost
Expenditure
₹838 Cr
Spent to date
Utilization
61.5%
Of revised budget
Cost Status
+36.0%
+₹361 Cr increase
Remaining
₹525 Cr
Budget left
Budget Utilization
61.5%Spent
₹838 Cr
Remaining
₹525 Cr
Total
₹1363 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1002 Cr
Revised Cost
₹1363 Cr
Increase
+₹361 Cr
Escalation
+36.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/05/2024
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹361 Cr (36.0%) from the original estimate of ₹1002 Cr.
Expenditure stands at ₹838 Cr, which is 61.5% of the revised project cost.
Remaining budget: ₹525 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of Old NH-20 New NH-154 Package-IA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1002.00 Cr, later revised to ₹1363.04 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of Old NH-20 New NH-154 "?
- 4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of Old NH-20 New NH-154 Package-IA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹1002 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1002 Cr and has been revised to ₹1363 Cr — a cost overrun of +36%. Expenditure to date: ₹838 Cr (61.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of O is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619153. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of HP/Punjab Border - Mo from km. 11.00 to km. 42.00 of O is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.