Original Cost
₹1002 Cr
Baseline estimate
Revised Cost
₹1363 Cr
Latest approved cost
Expenditure
₹580 Cr
Spent to date
Utilization
42.6%
Of revised budget
Cost Status
+36.0%
+₹361 Cr increase
Remaining
₹783 Cr
Budget left
Spent
₹580 Cr
Remaining
₹783 Cr
Total
₹1363 Cr
Original Cost
₹1002 Cr
Revised Cost
₹1363 Cr
Increase
+₹361 Cr
Escalation
+36.0%
Project Approved
Construction / Implementation
Original End Date
17/05/2024
Revised Completion
19/10/2026
Completed
Cost has increased by ₹361 Cr (36.0%) from the original estimate of ₹1002 Cr.
Expenditure stands at ₹580 Cr, which is 42.6% of the revised project cost.
Remaining budget: ₹783 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.